Other works


Retail Park “Da Vinci” in Fiumicino (RM)

Retail park with 60.000 m2 of surface on a 25 Hectares area; the activity consisted in  the construction of a foundation structure made by 70 piles, and a light structure for the slab on grade.

The activity includes:

  • 200.000  m3 of excavations and backfilling
  • 16.000  m of multiton piles
  • 28,000 m3 of structural concrete
  • 200.000 kg of reinforcing steel
  • 000 m2 of ventilated ceilings with 110/120 cm high plastic formwork
  • 7,000 m² of prefabricated Spiroll slabs.

Overall Design – Foundation structure construction

 

Client:  AIG LINCOLN ITALIA –(MI)

Project Amount : € 45.000.000,00

Works Amount: € 9.900.000,00

Design Amount: € 1.200.000,00

Dates : 2006 – 2007

Commercial Hub L14 Le Vignole  in Fiumicino (RM)

Design of a commercial hub with 60.000 m2 of surface, including a 10.000 m2 of hypermarket, n. 123 shops (40.000 m2) and common areas with 10.000 m2.

The activity includes:

  • 61.500 m2 of lime soil treatment
  • 30.000 m3 of excavations and backfilling
  • 60.000 m of multiton piles
  • 110.000 m2 of structures
  • 7,000 m² of prefabricated Spiroll slabs.

Overall Design –  Project management construction

Client:   III Iniziative Immobiliari Integrate SpA (RM)

Works Amount: 100.000,00

Design Amount: € 1.500.000,00

Dates: 2007 – 2008

Commercial Hub Gran Sasso  in Teramo

Design of a commercial hub with 29.700 m2 of surface, including a 10.500 m2 of hypermarket, n. 100 shops and n. 500 car parks.

Technical Due diligence –  Preliminary design management

Client: Foruminvest Italia –(MI)

Dates: 2006

Dependent School in Aviano ( PN ) – US Navy

Dependent school for NATO employers construction

Project management

Client: US Navy

Dates: 1998 – 2000

Tax Police headquarters (AN )

Construction of the Dorica Barracks in Ancona with staff accomodations

Construction Management

Client: Min. LLPP – Provv. OO.PP. Marche

General Contractor:  I.G.A. SpA

Dates: 1995 – 1998

Prison in Bologna

Enlargements

Construction Management

Client:  Min. LLPP – Provv. OO.PP. Emilia-Romagna

General Contractor:  I.G.A. SpA

Dates: 1995 – 1997

Maria della Speranza-Religious Salesians Complex (RM)

Construction of a parish center including: a church, offices, oratory, theater with 600 seats, outdoor sports areas and car parks

Construction Management

Client: Ispettoria Salesiana Romana

General Contractor:  Lispes Scarl (Lodigiani SpA – I.G.A. SpA)

Dates: 1991 – 1993

Flaminia 3 – ENEL Building (RM)

 Building office Construction for ENEL in Rome

Member of the Technical Committee

Client: ENEL SpA

General Contractor:  Olympic 90

Infrastructure Consortium ( Cogefar – IM.CO. – CCC – IGA -Gran Sasso )

Dates: 1990 – 1991

A14 Highway

Construction of the third lane of the A14 from  Solarolo to Roncadello in Forlì (9 Km)

Costs control

Client: Autostrade SpA

General Contractor:  IGA SPA

Dates: 1989 – 1990

4 Power Plants in Rome

Construction of n. 4 power plants (AM-MT) in Rome

Member of the Technical Committee

Client: ENEL SpA

General Contractor:  Consorzio Olimpico 90 Infrastrutture (Cogefar – IM.CO. – CCC-IGA – Coop. Gran Sasso)

Dates: 1989 – 1991

Enlargement of the Olympic Stadium in Rome – CONI

Demolition and construction of the Olympic stadium in Rome for the 1990 World soccer cup (80.000 seats)

Member of the Technical Committee

Client: CONI

General Contractor:  Olimpico 90 Scarl (Cogefar-IM.CO.-CCC-IGA-Gran Sasso)

Dates: 1989 – 1991

2nd ITP project  ( Kirkuk – Ceyhan Oil Pipeline )

Pipeline of 600 miles (970 km) – with related works – which connects the oil fields of southern Iraq to the Ceyhan terminal in Turkey

Client: Iraq National Oil Company

General Contractor:  SAIPEM SPA (MI)

Dates: 1986 – 1987